Contractors suspended over ‘extremely serious’ Queen Mary Hospital lift defects

Authorities say 24 of 28 lifts in the new clinical block were affected, delaying the launch of clinical services until repairs are completed

3-MIN READ3-MIN
5
Listen
Damaged electronic components, faulty wiring connections and poor installation workmanship were among the problems affecting 24 of the 28 newly installed lifts in Clinical Block 1. Photo: Karma Lo
Faulty lifts in Clinical Block 1 at Queen Mary Hospital have delayed the launch of all clinical services at the building. Photo: Karma Lo
The faults caused lifts to start or stop unevenly, halt at positions that were not level with the floor, or fail to open their doors. Photo: Karma Lo
Wynna Wong

Hong Kong authorities have suspended the main contractor and lift subcontractor working on a new clinical block at Queen Mary Hospital from public works tenders after serious defects left most lifts unreliable and delayed the launch of services.

The Architectural Services Department said in a social media post late on Friday that the contractors’ poor performance had been recorded in assessment reports.

It added that the firms would be required to bear the full cost of remedial works and could face claims for losses arising from delays to the HK$15.15 billion (US$1.93 billion) redevelopment project at the Pok Fu Lam hospital.

“In accordance with contractual mechanisms, we have also reflected the contractor’s and works subcontractor’s poor performance on the project in their assessment reports and suspended their eligibility to tender for public works contracts,” the department said.

The main contractor for the first phase of the redevelopment was the Paul Y-Able Joint Venture. The lift subcontractor, Anlev Elex Elevator, is a subsidiary of ATAL Engineering Group, founded by Otto Poon Lok-to, the husband of former justice secretary Teresa Cheng Yeuk-wah.

The department said damaged electronic components, faulty wiring connections and poor installation workmanship were among the problems affecting 24 of the 28 newly installed lifts in Clinical Block 1.